(via TheNewswire)
(ACN:007 626 575) (ASX/TSXV:JRV) (OTC:JRVMF) Corporate Information 1,519.7M Ordinary Shares 93.6M Options 4.4M Performance Rights Non-Executive Chairman CEO and Executive Director Non-Executive Directors Company Secretary Contact Details Suite 2.03,
P: +61 (3) 9583 0498 E: admin@jervoisglobal.com W: www.jervoisglobal.com | Highlights Idaho Cobalt Operations (“ICO”),
Jervois Finland:
São Miguel Paulista (“SMP”) Nickel and
Corporate:
|
Idaho Cobalt Operations (“ICO”),
Jervois celebrated the official opening of ICO on
The ceremony took place at 8,100 feet, surrounded by the
ICO is the only primary cobalt mine in the
Jervois commenced the first stage of plant commissioning at ICO following the opening, with commissioning expected to continue throughout October and November. Commercial concentrate production is expected in Q4 2022. Jervois expects to achieve full nameplate capacity by the end of Q1 2023.
Ore delivery to the plant on the ICO site is expected to begin during Q4 2022, with multiple ore faces now available for production mining. Underground mine infrastructure, including the underground fuel island, triple clarifying sumps and the main shop, are nearing completion. Mine development continues with a focus on vertical development to support additional production ore faces, reducing risk to ore delivery and increasing optionality for blending.
During September, the ICO mining camp opened and is now operating at 90% capacity. The mining camp consists of 102 individual rooms with ensuites, a dining facility, laundry facilities and recreation facilities. During Q4 2022, the “miners’ dry” is expected to be installed and commissioned. The ICO mining camp will deliver increased safety benefits with reduced travel and improved fatigue management, as well as increased productivity from increased working hours, efficient shift changes and the ability to continue construction activities on a 24 hours / 7 days a week basis.
At the end of Q3 2022, ICO construction was at 95% engineering completion and 71% construction completion. Major equipment installs including the SAG mill, ball mill, jaw crusher, fine ore bin, raw water tank, process water tank, copper and cobalt flotation cells are now complete. Commissioning on key utility systems such as process water delivery has commenced. Concrete work for the project is nearing completion, as construction focus moves to electrical and piping installation with the first installs occurring during the period.
During Q3 2022, expansion of the Tailings and Waste Storage Facility (“TWSF”) commenced with all earthmoving, lining and piping completed, with only the installation of the aggregate overliner remaining for completion in Q4 2022.
At the end of September, Jervois had spent
Drilling at ICO
During 2022, Jervois commenced a
An updated Australian JORC 2012 and Canadian National Instrument (“NI”) 43-101 Mineral Reserve and Resource Estimate is expected to be published in Q2 2023.
Offtake
As there are no cobalt refineries in the
Jervois will sell copper concentrate from ICO into North American markets.
Operating Costs
ICO construction has taken place across a period of rising inflation in the
Strategic Importance of ICO
ICO became an economically viable project as cobalt prices increased, and global geopolitical perspectives evolved with governments placing increased importance on critical mineral production in their own countries or in friendly jurisdictions. ICO will be a key contributor to
Jervois hopes to progress its engagement with the
Jervois is proud of its ESG record to date and plans to continue to demonstrate its ability to operate ICO with strong environmental stewardship. Jervois looks forward to continuing its productive relationship with its regulators, including the
Jervois may pursue financing options for ICO and / or in other parts of its business with the
Jervois Finland Q3 2022 Results
Quarterly revenue:
US$84.6 million (Q2 2022:US$91.2 million )Adjusted EBITDA -
US$0.6 million (Q2 2022:US$11.9 million )Adjusted EBITDA margin: -0.7% (Q2 2022: 13.0%)
Cobalt sales volume: 1,407 metric tonnes (Q2 2022: 1,139 metric tonnes)
Production volume: 1,586 metric tonnes (Q2 2022: 1,145 metric tonnes)
Sales and Marketing
The cobalt market has stabilised after the recent downturn where the global macroeconomic situation, along with continuing Covid-related lockdowns, temporarily dampened demand. Risks of disruptions to global supply from the
Jervois’ outlook for key market segments is summarised below.
Batteries:
Lithium cobalt oxide“LCO”) chemistry into
China remains weak; whilst electric vehicle demand is growing rapidly, lithium ion battery usage into cell phones, tablets and computers remains a large driver of the cobalt market.Jervois Finland sales to the battery market remain sluggish as producers sit on high levels of inventory and programmes have been delayed. A lack of semiconductors has been cited as the reason for much of the softness.
Looking to 2023, Jervois’s customers will carry inventory across the remainder of 2022 and into early 2023, and cobalt sales are expected to begin accelerating across next year as the situation both improves, and electric vehicle penetration rates continue to rise.
Jervois’s commercial team are in active negotiations with major European,
U.S. and Japanese battery plants regarding a significant uptick in cobalt demand that is steadily projected across 2023, and then aggressively from early 2024.The recent
U.S. Inflation Reduction Act 2022 is expected to have a profound impact not only on trade flows but also industry capital allocation, as the economic benefits associated the legislation trigger both new investment decisions into America, and prior announcements to be revisited in light ofU.S. incentives.
Chemicals, Catalysts and Ceramics:
Catalysts: cobaltcarbonate sales to Jervois Finland’s customer base continue to meet expectations, which are currently at the lower end of historical bands particularly inhydrodesulphurization (“HDS”) catalysts. Modest growth is expected in 2023, with gas to liquids (“GTL”) catalysts holding up better than HDS.
Chemicals:consumption remains steady, particularly in
Asia , of cobalt hydroxide for rubber adhesion promoters and coatings, while Western demand is weakening. Cobalt sulphate usage in copper electrowinning remained steady.Ceramics:high energy costs continue to dampen demand at ceramic tile and pigment producers, particularly in
Europe , while Chinese cobalt oxide producers remain active participants in global markets as a result of their country’s continued ‘zero Covid’ policy and consequential impact on their domestic economy.
Powder Metallurgy:
Jervois has relatively limited direct sales, but aerospace (the second largest consumer of cobalt after batteries) has picked up substantially post Covid, with a strong outlook for 2023. Rising demand in aerospace is being supported by increases across both civilian and defense industry sectors. Cobalt metal (of which aerospace consumes) has the most pronounced impact on Western pricing, published by Fastmarkets Metal Bulletin.
Jervois Finland cobalt powder sales have softened, as recession concerns have hard metal and diamond tool customers reducing inventories and forecasting limited growth in 2023.
European customers are expressing concern that lack of natural gas supplies could impact business activity levels, depending on the harshness of the winter and geopolitical situation following Russia’s invasion of
Ukraine .
Jervois Finland achieved production of 1,586 metric tonnes and sales of 1,407 metric tonnes in the quarter, an increase over the prior quarter of +38.5% (which was affected by a scheduled annual maintenance shutdown) and +23.5%, respectively. Quarterly sales volumes were restored to historic average levels as market demand stabilised. Jervois continues to pursue new market development initiatives, with a focus on expanding and deepening relationships in the high-growth battery segment, to underpin future growth.
The business is pursuing a disciplined approach to managing its cobalt inventories. Inventories continue to be above target levels at 30 September. The pace of inventory reduction is being optimised for market conditions. Working capital is discussed further below.
Financial Performance2
Jervois Finland achieved revenue of
Figure 1: Jervois Finland Revenue (US$M, unaudited)
Jervois Finland revenue was 8% lower than the prior quarter. Sales volumes were 23% higher, offset by the impact of a 32% decline in the average cobalt price.
Adjusted Jervois Finland EBITDA for Q3 2022 of (
Figure 2: Jervois Finland Adjusted EBITDA (US$M, unaudited)
Figure 3: Jervois Finland Adjusted EBITDA Margin (%, unaudited)
Year-to-date Adjusted EBITDA is
Sales volume guidance for the full year is 5,400 to 5,600 mt. Adjusted EBITDA guidance for the full year is
Working Capital
Net working capital was stable relative to the prior quarter. Cobalt inventories were 2,687 mt at 30 September, compared to 2,491 mt at 30 June. Total inventory volume at ~160 days remains in excess of target levels (90 to 110 days). A key driver is the cobalt hydroxide supply catch-up that occurred in Q2 2022 following significant interruptions to logistics over the prior 12 months. Jervois has elected to stage the inventory unwind into 2023 with the aim of preserving value in periods where the market has been relatively illiquid and supporting management of near-term risks around raw materials supply. Jervois anticipates that cash progressively released from working capital reductions will be used to meet partial repayment of the Mercuria working capital facility.
The Net Realisable Value (“NRV”) of cobalt inventories as at
São Miguel Paulista (“SMP”) Nickel and
In September, Jervois received an Environmental Installation License (the “LPI”) for its São Miguel Paulista (“SMP”) nickel cobalt refinery in São Paulo. This license from the State environmental regulator, Companhia Ambiental do Estado de São Paulo (“CETESB”), represents São Paulo State approval for construction of the Stage 1 SMP restart, another important milestone for the project.
Activities in support of the restart of the refinery are advancing. Detailed engineering and execution planning are advancing in partnership with Ausenco. Commercial activities are advancing with increased confidence in an ability to achieve future supply of nickel intermediate feed products on more attractive terms than assumed in the published Bankable Feasibility Study (“BFS”) (see announcement on
Jervois forecasts production of 10,000 metric tonnes per annum (“mtpa”) and 2,000 mtpa of refined nickel and cobalt metal cathode respectively for the Stage 1
Jervois’ 100%-owned Nico Young nickel and cobalt project envisages heap leaching nickel and cobalt laterite ore to produce either an intermediate MHP or refining through to battery grade nickel sulphate and cobalt in refined sulphide.
Planning for Jervois’s drilling campaign at Nico Young is well underway, with an initial focus on converting inferred resources into the indicated category. An inspection will be undertaken in late October to assess the local conditions following significant local rainfall, and review key activities for the planned drilling program expected to commence in
Corporate Activities
Liquidity
Jervois closed the quarter with
Investor Relations
In August, Jervois’ Chief Executive Officer, Mr.
Environmental, Social, Governance and Compliance
Responsible Supply Chains
Jervois established a
Jervois is well positioned to leverage the expertise, policies and processes in place at Jervois Finland, the first cobalt chemical and metal powder producer conformant to RMI’s Downstream Assessment Program. In conjunction, Jervois’ Group Manager – ESG and Jervois Finland’s Director of Plant Support and Administration conducted a 10-day visit to a number of supplier sites in order to assess Jervois’ upstream ESG compliance. All supplier sites visited were observed to be aligned with international standards, including through having well-established risk management frameworks.
Climate Action
A series of near-term, carbon emission reduction measures are already underway at Jervois Finland, including the securing of access to long term (10 year) renewable electricity representing approximately two thirds of its total annual current (prior to expansion) power consumption commencing in 2024 and 2025 as announced on
Diversity and Inclusion
Jervois recognises that, by developing inclusive working conditions and fostering a diverse workforce, we can create a pipeline for promotion from within while creating conditions to attract talent from outside. Benefits in terms of productivity, innovation, decision-making, employee satisfaction and other factors are well-established. A Diversity and Inclusion Roadmap is being prepared, led by the
Jervois Whistleblower and Grievance Process
Reinforcement of Jervois’ whistleblower and operations-level grievance processes is essential to compliance with acceptable standards of practice under industry ESG standards while helping to strengthen community relations, create inclusive working conditions, support responsible supply chains, and foster continuous improvement. Jervois has engaged People InTouch to provide organisational support, including training, to improve existing whistleblower and grievance mechanisms and establish a “Speak Up” culture at all levels of the organisation.
Engaging the
During the quarter, Jervois continued to engage in the
Jervois also continued to engage with the
Management Updates
Post quarter-end in October, Jervois appointed Mr.
Acting EGM Brazil, Mr. Valdecir Botassini (refer to announcement dated
Exploration and Development Expenditure
No material cash expenditure on exploration and development was incurred during the quarter.
Insider Compensation Reporting
During the quarter,
Non-Core Assets
Jervois’ non-core assets are summarised on the Company’s website.
ASX Waiver Information
On
Jervois shares issued in the quarter on exercise of eCobalt options: | Nil |
eCobalt options remaining4 | |
1,179,750 1,980,000 | eCobalt options exercisable until eCobalt options exercisable until |
3,159,750 |
By Order of the Board
Chief Executive Officer,
For further information, please contact:
Investors and analysts: Chief Financial Officer Jervois GlobalLimited james.may@jervoisglobal.com | Media: nathan.ryan@nwrcommunications.com.au Mob: +61 420 582 887 |
Forward-Looking Statements
This news release may contain certain “Forward-Looking Statements” within the meaning of the United States Private Securities Litigation Reform Act of 1995 and applicable Canadian securities laws. When used in this news release, the words “anticipate”, “believe”, “estimate”, “expect”, “target, “plan”, “forecast”, “may”, “schedule” and other similar words or expressions identify forward-looking statements or information. These forward-looking statements or information may relate to future EBITDA for the group, operations at Jervois Finland, construction work undertaken at ICO, timing of production at ICO, preparation of studies on the
Neither
Basis of Preparation of Financial Information
Historical and forecast financial information
Historical financial information for Jervois Finland prior to acquisition by
Financial information presented for periods after the acquisition on
EBITDA for historical periods is presented as net income after adding back tax, interest, depreciation and extraordinary items and is a non-IFRS/non-GAAP measure.
The Jervois Finland 2022 guidance consists of actual results for January to September and forecast results for October to December. The forecast period includes an assumption of a Q4 2022 forecast Fastmarkets Metal Bulletin Standard
Reconciliation of NPAT to EBITDA and Adjusted EBITDA
EBITDA is a non-IFRS financial measure. EBITDA is presented as net income after adding back interest, tax, depreciation and amortisation, and extraordinary items. Adjusted EBITDA represents EBITDA adjusted to exclude items which do not reflect the underlying performance of the company’s operations. Exclusions from adjusted EBITDA are items that require exclusion in order to maximise insight and consistency on the financial performance of the company’s operations.
Exclusions include gains/losses on disposals, impairment charges (or reversals), certain derivative items, NRV adjustments to inventories*, and one-off costs related to post-acquisition integration.
*NRV is excluded from Adjusted EBITDA given the adjustment occurs in times of extreme and rapid cobalt price movements. This approach is consistent with the scope of exclusions previously disclosed by Jervois, which includes impairments and reversals, and the 2019 proforma financials disclosed as part of the
Tenements
Australian Tenements
Description | Tenement number | Interest owned % | |
Ardnaree (NSW) | EL 5527 | 100.0 | |
Thuddungra (NSW) | EL 5571 | 100.0 | |
Nico Young (NSW) | EL 8698 | 100.0 | |
West Arunta (WA) | E80 4820 | 17.9 | |
West Arunta (WA) | E80 4986 | 17.9 | |
West Arunta (WA) | E80 4987 | 17.9 |
Uganda Exploration Licences | |||
Description | Exploration Licence number | Interest owned % | |
Kilembe Area | EL0292 | 100.0 | |
Kilembe Area | EL0012 | 100.0 |
Idaho Cobalt Operations – 100% Interest owned | |||
Claim | County # | IMC # | |
SUN 1 | 222991 | 174156 | |
SUN 2 | 222992 | 174157 | |
SUN 3 Amended | 245690 | 174158 | |
SUN 4 | 222994 | 174159 | |
SUN 5 | 222995 | 174160 | |
SUN 6 | 222996 | 174161 | |
SUN 7 | 224162 | 174628 | |
SUN 8 | 224163 | 174629 | |
SUN 9 | 224164 | 174630 | |
SUN 16 Amended | 245691 | 177247 | |
SUN 18 Amended | 245692 | 177249 | |
Sun 19 | 277457 | 196394 | |
228059 | 176755 | ||
228060 | 176756 | ||
228049 | 176769 | ||
228050 | 176770 | ||
228051 | 176771 | ||
DEWEY FRAC Amended | 248739 | 177253 | |
Powder 1 | 269506 | 190491 | |
Powder 2 | 269505 | 190492 | |
LDC-1 | 224140 | 174579 | |
LDC-2 | 224141 | 174580 | |
LDC-3 | 224142 | 174581 | |
LDC-5 | 224144 | 174583 | |
LDC-6 | 224145 | 174584 | |
LDC-7 | 224146 | 174585 | |
LDC-8 | 224147 | 174586 | |
LDC-9 | 224148 | 174587 | |
LDC-10 | 224149 | 174588 | |
LDC-11 | 224150 | 174589 | |
LDC-12 | 224151 | 174590 | |
LDC-13 Amended | 248718 | 174591 | |
LDC-14 Amended | 248719 | 174592 | |
LDC-16 | 224155 | 174594 | |
LDC-18 | 224157 | 174596 | |
LDC-20 | 224159 | 174598 | |
LDC-22 | 224161 | 174600 | |
LDC FRAC 1 Amended | 248720 | 175880 | |
LDC FRAC 2 Amended | 248721 | 175881 | |
LDC FRAC 3 Amended | 248722 | 175882 | |
LDC FRAC 4 Amended | 248723 | 175883 | |
LDC FRAC 5 Amended | 248724 | 175884 | |
RAM 1 | 228501 | 176757 | |
RAM 2 | 228502 | 176758 | |
RAM 3 | 228503 | 176759 | |
RAM 4 | 228504 | 176760 | |
RAM 5 | 228505 | 176761 | |
RAM 6 | 228506 | 176762 | |
RAM 7 | 228507 | 176763 | |
RAM 8 | 228508 | 176764 | |
RAM 9 | 228509 | 176765 | |
RAM 10 | 228510 | 176766 | |
RAM 11 | 228511 | 176767 | |
RAM 12 | 228512 | 176768 | |
RAM 13 Amended | 245700 | 181276 | |
RAM 14 Amended | 245699 | 181277 | |
RAM 15 Amended | 245698 | 181278 | |
RAM 16 Amended | 245697 | 181279 | |
245696 | 178081 | ||
245695 | 178082 | ||
245694 | 178083 | ||
245693 | 178084 | ||
HZ 1 | 224173 | 174639 | |
HZ 2 | 224174 | 174640 | |
HZ 3 | 224175 | 174641 | |
HZ 4 | 224176 | 174642 | |
HZ 5 | 224413 | 174643 | |
HZ 6 | 224414 | 174644 | |
HZ 7 | 224415 | 174645 | |
HZ 8 | 224416 | 174646 | |
HZ 9 | 224417 | 174647 | |
HZ 10 | 224418 | 174648 | |
HZ 11 | 224419 | 174649 | |
HZ 12 | 224420 | 174650 | |
HZ 13 | 224421 | 174651 | |
HZ 14 | 224422 | 174652 | |
HZ 15 | 231338 | 178085 | |
HZ 16 | 231339 | 178086 | |
HZ 18 | 231340 | 178087 | |
HZ 19 | 224427 | 174657 | |
Z 20 | 224428 | 174658 | |
HZ 21 | 224193 | 174659 | |
HZ 22 | 224194 | 174660 | |
HZ 23 | 224195 | 174661 | |
HZ 24 | 224196 | 174662 | |
HZ 25 | 224197 | 174663 | |
HZ 26 | 224198 | 174664 | |
HZ 27 | 224199 | 174665 | |
HZ 28 | 224200 | 174666 | |
HZ 29 | 224201 | 174667 | |
HZ 30 | 224202 | 174668 | |
HZ 31 | 224203 | 174669 | |
HZ 32 | 224204 | 174670 | |
HZ FRAC | 228967 | 177254 | |
JC 1 | 224165 | 174631 | |
JC 2 | 224166 | 174632 | |
JC 3 | 224167 | 174633 | |
JC 4 | 224168 | 174634 | |
JC 5 Amended | 245689 | 174635 | |
JC 6 | 224170 | 174636 | |
JC FR 7 | 224171 | 174637 | |
JC FR 8 | 224172 | 174638 | |
JC 9 | 228054 | 176750 | |
JC 10 | 228055 | 176751 | |
JC 11 | 228056 | 176752 | |
JC-12 | 228057 | 176753 | |
JC-13 | 228058 | 176754 | |
JC 14 | 228971 | 177250 | |
JC 15 | 228970 | 177251 | |
JC 16 | 228969 | 177252 | |
JC 17 | 259006 | 187091 | |
JC 18 | 259007 | 187092 | |
JC 19 | 259008 | 187093 | |
JC 20 | 259009 | 187094 | |
JC 21 | 259010 | 187095 | |
JC 22 | 259011 | 187096 | |
CHELAN NO. 1 Amended | 248345 | 175861 | |
GOOSE 2 Amended | 259554 | 175863 | |
GOOSE 3 | 227285 | 175864 | |
GOOSE 4 Amended | 259553 | 175865 | |
GOOSE 6 | 227282 | 175867 | |
GOOSE 7 Amended | 259552 | 175868 | |
GOOSE 8 Amended | 259551 | 175869 | |
GOOSE 10 Amended | 259550 | 175871 | |
GOOSE 11 Amended | 259549 | 175872 | |
GOOSE 12 Amended | 259548 | 175873 | |
GOOSE 13 | 228028 | 176729 | |
GOOSE 14 Amended | 259547 | 176730 | |
GOOSE 15 | 228030 | 176731 | |
GOOSE 16 | 228031 | 176732 | |
GOOSE 17 | 228032 | 176733 | |
GOOSE 18 Amended | 259546 | 176734 | |
GOOSE 19 Amended | 259545 | 176735 | |
GOOSE 20 | 228035 | 176736 | |
GOOSE 21 | 228036 | 176737 | |
GOOSE 22 | 228037 | 176738 | |
GOOSE 23 | 228038 | 176739 | |
GOOSE 24 | 228039 | 176740 | |
GOOSE 25 | 228040 | 176741 | |
SOUTH ID 1 Amended | 248725 | 175874 | |
SOUTH ID 2 Amended | 248726 | 175875 | |
SOUTH ID 3 Amended | 248727 | 175876 | |
SOUTH ID 4 Amended | 248717 | 175877 | |
SOUTH ID 5 Amended | 248715 | 176743 | |
SOUTH ID 6 Amended | 248716 | 176744 | |
South ID 7 | 306433 | 218216 | |
South ID 8 | 306434 | 218217 | |
South ID 9 | 306435 | 218218 | |
South ID 10 | 306436 | 218219 | |
South ID 11 | 306437 | 218220 | |
South ID 12 | 306438 | 218221 | |
South ID 13 | 306439 | 218222 | |
South ID 14 | 306440 | 218223 | |
OMS-1 | 307477 | 218904 | |
Chip 1 | 248956 | 184883 | |
Chip 2 | 248957 | 184884 | |
Chip 3 Amended | 277465 | 196402 | |
Chip 4 Amended | 277466 | 196403 | |
Chip 5 Amended | 277467 | 196404 | |
Chip 6 Amended | 277468 | 196405 | |
Chip 7 Amended | 277469 | 196406 | |
Chip 8 Amended | 277470 | 196407 | |
Chip 9 Amended | 277471 | 196408 | |
Chip 10 Amended | 277472 | 196409 | |
Chip 11 Amended | 277473 | 196410 | |
Chip 12 Amended | 277474 | 196411 | |
Chip 13 Amended | 277475 | 196412 | |
Chip 14 Amended | 277476 | 196413 | |
Chip 15 Amended | 277477 | 196414 | |
Chip 16 Amended | 277478 | 196415 | |
Chip 17 Amended | 277479 | 196416 | |
Chip 18 Amended | 277480 | 196417 | |
Sun 20 | 306042 | 218133 | |
Sun 21 | 306043 | 218134 | |
Sun 22 | 306044 | 218135 | |
Sun 23 | 306045 | 218136 | |
Sun 24 | 306046 | 218137 | |
Sun 25 | 306047 | 218138 | |
Sun 26 | 306048 | 218139 | |
Sun 27 | 306049 | 218140 | |
Sun 28 | 306050 | 218141 | |
Sun 29 | 306051 | 218142 | |
Sun 30 | 306052 | 218143 | |
Sun 31 | 306053 | 218144 | |
Sun 32 | 306054 | 218145 | |
Sun 33 | 306055 | 218146 | |
Sun 34 | 306056 | 218147 | |
Sun 35 | 306057 | 218148 | |
Sun 36 | 306058 | 218149 | |
Chip 21 Fraction | 306059 | 218113 | |
Chip 22 Fraction | 306060 | 218114 | |
Chip 23 | 306025 | 218115 | |
Chip 24 | 306026 | 218116 | |
Chip 25 | 306027 | 218117 | |
Chip 26 | 306028 | 218118 | |
Chip 27 | 306029 | 218119 | |
Chip 28 | 306030 | 218120 | |
Chip 29 | 306031 | 218121 | |
Chip 30 | 306032 | 218122 | |
Chip 31 | 306033 | 218123 | |
Chip 32 | 306034 | 218124 | |
Chip 33 | 306035 | 218125 | |
Chip 34 | 306036 | 218126 | |
Chip 35 | 306037 | 218127 | |
Chip 36 | 306038 | 218128 | |
Chip 37 | 306039 | 218129 | |
Chip 38 | 306040 | 218130 | |
Chip 39 | 306041 | 218131 | |
Chip 40 | 307491 | 218895 | |
DRC NW 1 | 307492 | 218847 | |
DRC NW 2 | 307493 | 218848 | |
DRC NW 3 | 307494 | 218849 | |
DRC NW 4 | 307495 | 218850 | |
DRC NW 5 | 307496 | 218851 | |
DRC NW 6 | 307497 | 218852 | |
DRC NW 7 | 307498 | 218853 | |
DRC NW 8 | 307499 | 218854 | |
DRC NW 9 | 307500 | 218855 | |
DRC NW 10 | 307501 | 218856 | |
DRC NW 11 | 307502 | 218857 | |
DRC NW 12 | 307503 | 218858 | |
DRC NW 13 | 307504 | 218859 | |
DRC NW 14 | 307505 | 218860 | |
DRC NW 15 | 307506 | 218861 | |
DRC NW 16 | 307507 | 218862 | |
DRC NW 17 | 307508 | 218863 | |
DRC NW 18 | 307509 | 218864 | |
DRC NW 19 | 307510 | 218865 | |
DRC NW 20 | 307511 | 218866 | |
DRC NW 21 | 307512 | 218867 | |
DRC NW 22 | 307513 | 218868 | |
DRC NW 23 | 307514 | 218869 | |
DRC NW 24 | 307515 | 218870 | |
DRC NW 25 | 307516 | 218871 | |
DRC NW 26 | 307517 | 218872 | |
DRC NW 27 | 307518 | 218873 | |
DRC NW 28 | 307519 | 218874 | |
DRC NW 29 | 307520 | 218875 | |
DRC NW 30 | 307521 | 218876 | |
DRC NW 31 | 307522 | 218877 | |
DRC NW 32 | 307523 | 218878 | |
DRC NW 33 | 307524 | 218879 | |
DRC NW 34 | 307525 | 218880 | |
DRC NW 35 | 307526 | 218881 | |
DRC NW 36 | 307527 | 218882 | |
DRC NW 37 | 307528 | 218883 | |
DRC NW 38 | 307529 | 218884 | |
DRC NW 39 | 307530 | 218885 | |
DRC NW 40 | 307531 | 218886 | |
DRC NW 41 | 307532 | 218887 | |
DRC NW 42 | 307533 | 218888 | |
DRC NW 43 | 307534 | 218889 | |
DRC NW 44 | 307535 | 218890 | |
DRC NW 45 | 307536 | 218891 | |
DRC NW 46 | 307537 | 218892 | |
DRC NW 47 | 307538 | 218893 | |
DRC NW 48 | 307539 | 218894 | |
EBatt 1 | 307483 | 218896 | |
EBatt 2 | 307484 | 218897 | |
EBatt 3 | 307485 | 218898 | |
EBatt 4 | 307486 | 218899 | |
EBatt 5 | 307487 | 218900 | |
EBatt 6 | 307488 | 218901 | |
EBatt 7 | 307489 | 218902 | |
EBatt 8 | 307490 | 218903 | |
OMM-1 | 307478 | 218905 | |
OMM-2 | 307479 | 218906 | |
OMN-2 | 307481 | 218908 | |
OMN-3 | 307482 | 218909 | |
BTG-1 | 307471 | 218910 | |
BTG-2 | 307472 | 218911 | |
BTG-3 | 307473 | 218912 | |
BTG-4 | 307474 | 218913 | |
BTG-5 | 307475 | 218914 | |
BTG-6 | 307476 | 218915 | |
NFX 17 | 307230 | 218685 | |
NFX 18 | 307231 | 218686 | |
NFX 19 | 307232 | 218687 | |
NFX 20 | 307233 | 218688 | |
NFX 21 | 307234 | 218689 | |
NFX 22 | 307235 | 218690 | |
NFX 23 | 307236 | 218691 | |
NFX 24 | 307237 | 218692 | |
NFX 25 | 307238 | 218693 | |
NFX 30 | 307243 | 218698 | |
NFX 31 | 307244 | 218699 | |
NFX 32 | 307245 | 218700 | |
NFX 33 | 307246 | 218701 | |
NFX 34 | 307247 | 218702 | |
NFX 35 | 307248 | 218703 | |
NFX 36 | 307249 | 218704 | |
NFX 37 | 307250 | 218705 | |
NFX 38 | 307251 | 218706 | |
NFX 42 | 307255 | 218710 | |
NFX 43 | 307256 | 218711 | |
NFX 44 | 307257 | 218712 | |
NFX 45 | 307258 | 218713 | |
NFX 46 | 307259 | 218714 | |
NFX 47 | 307260 | 218715 | |
NFX 48 | 307261 | 218716 | |
NFX 49 | 307262 | 218717 | |
NFX 50 | 307263 | 218718 | |
NFX 56 | 307269 | 218724 | |
NFX 57 | 307270 | 218725 | |
NFX 58 | 307271 | 218726 | |
NFX 59 | 307272 | 218727 | |
NFX 60 Amended | 307558 | 218728 | |
NFX 61 | 307274 | 218729 | |
NFX 62 | 307275 | 218730 | |
NFX 63 | 307276 | 218731 | |
NFX 64 | 307277 | 218732 | |
OMN-1 revised | 315879 | 228322 |
Appendix 5B
Mining exploration entity or oil and gas exploration entity
quarterly cash flow report
ABN | Quarter ended (“current quarter”) | |
52 007 626 575 |
Consolidated statement of cash flows | Current quarter | Year to date (9 months) $US’000 | |
1. | Cash flows from operating activities | 83,776 | 277,884 |
1.1 | Receipts from customers | ||
1.2 | Payments for | - | - |
| |||
| - | - | |
| (96,141) | (310,140) | |
| (1,669) | (4,988) | |
| (1,519) | (4,329) | |
1.3 | Dividends received (see note 3) | - | - |
1.4 | Interest received | 87 | 94 |
1.5 | Interest and other costs of finance paid | (8,160) | (16,789) |
1.6 | Income taxes paid | (1,646) | (5,771) |
1.7 | Government grants and tax incentives | - | - |
1.8 | Other – incl. business development costs and SMP BFS costs | (1,245) | (3,814) |
1.9 | Net cash from / (used in) operating activities | (26,517) | (67,853) |
2. | Cash flows from investing activities | - | - |
2.1 | Payments to acquire or for: | ||
| |||
| - | - | |
| (35,053) | (84,110) | |
| (35) | (85) | |
| - | - | |
| - | - | |
| - | - | |
2.2 | Proceeds from the disposal of: | - | - |
| |||
| - | - | |
| 20 | 1,250 | |
| - | - | |
| 186 | 186 | |
2.3 | Cash flows from loans to other entities | - | - |
2.4 | Dividends received (see note 3) | - | - |
2.5 | Other – SMP Refinery Purchase: lease payment | - | - |
2.6 | Net cash from / (used in) investing activities | (34,882) | (82,759) |
3. | Cash flows from financing activities | - | - |
3.1 | Proceeds from issues of equity securities (excluding convertible debt securities) | ||
3.2 | Proceeds from issue of convertible debt securities | - | - |
3.3 | Proceeds from exercise of options | - | 221 |
3.4 | Transaction costs related to issues of equity securities or convertible debt securities | - | (847) |
3.5 | Proceeds from borrowings | 57,250 | 156,000 |
3.6 | Repayment of borrowings | - | - |
3.7 | Transaction costs related to loans and borrowings | - | - |
3.8 | Dividends paid | - | - |
3.9 | Other – incl. lease liabilities | (1,100) | (1,318) |
3.10 | Net cash from / (used in) financing activities | 56,150 | 154,056 |
4. | Net increase / (decrease) in cash and cash equivalents for the period | ||
4.1 | Cash and cash equivalents at beginning of period | 57,560 | 49,181 |
4.2 | Net cash from / (used in) operating activities (item 1.9 above) | (26,517) | (67,853) |
4.3 | Net cash from / (used in) investing activities (item 2.6 above) | (34,882) | (82,759) |
4.4 | Net cash from / (used in) financing activities (item 3.10 above) | 56,150 | 154,056 |
4.5 | Effect of movement in exchange rates on cash held | 8 | (306) |
4.6 | Cash and cash equivalents at end of period | 52,319 | 52,319 |
5. | Reconciliation of cash and cash equivalents | Current quarter | Previous quarter |
5.1 | Bank balances | 52,319 | 57,560 |
5.2 | Call deposits | - | - |
5.3 | Bank overdrafts | - | - |
5.4 | Other (provide details) | - | - |
5.5 | Cash and cash equivalents at end of quarter (should equal item 4.6 above) | 52,319 | 57,560 |
6. | Payments to related parties of the entity and their associates | Current quarter |
6.1 | Aggregate amount of payments to related parties and their associates included in item 1 | 156 |
6.2 | Aggregate amount of payments to related parties and their associates included in item 2 | - |
Note: if any amounts are shown in items 6.1 or 6.2, your quarterly activity report must include a description of, and an explanation for, such payments. |
7. | Financing facilities Add notes as necessary for an understanding of the sources of finance available to the entity. | Total facility amount at quarter end | Amount drawn at quarter end |
7.1 | Bond Facility1 | 100,000 | 100,000 |
7.2 | Secured Revolving Credit Facility2 | 150,000 | 100,000 |
7.3 | Other | - | - |
7.4 | Total financing facilities | 250,000 | 200,000 |
7.5 | Unused financing facilities available at quarter end ($US’000) | 50,000 | |
7.6 | Include in the box below a description of each facility above, including the lender, interest rate, maturity date and whether it is secured or unsecured. If any additional financing facilities have been entered into or are proposed to be entered into after quarter end, include a note providing details of those facilities as well. | ||
On Key terms:
On Key terms:
|
8. | Estimated cash available for future operating activities | $US’000 |
8.1 | Net cash from / (used in) operating activities (item 1.9) | (26,517) |
8.2 | (Payments forexploration & evaluation classified as investing activities)(item 2.1(d)) | (35) |
8.3 | Total relevant outgoings (item 8.1 + item 8.2) | (26,552) |
8.4 | Cash and cash equivalents at quarter end (item 4.6) | 52,319 |
8.5 | Unused finance facilities available at quarter end (item 7.5) | 50,000 |
8.6 | Total available funding (item 8.4 + item 8.5) | 102,319 |
8.7 | Estimated quarters of funding available (item 8.6 divided by item 8.3) | 3.85 |
Note: if the entity has reported positive relevant outgoings (i.e., a net cash inflow) in item 8.3, answer item 8.7 as “N/A”. Otherwise, a figure for the estimated quarters of funding available must be included in item 8.7. | ||
8.8 | If item 8.7 is less than 2 quarters, please provide answers to the following questions: | |
8.8.1 Does the entity expect that it will continue to have the current level of net operating cash flows for the time being and, if not, why not? | ||
Answer: N/A | ||
8.8.2 Has the entity taken any steps, or does it propose to take any steps, to raise further cash to fund its operations and, if so, what are those steps and how likely does it believe that they will be successful? | ||
Answer: N/A | ||
8.8.3 Does the entity expect to be able to continue its operations and to meet its business objectives and, if so, on what basis? | ||
Answer: N/A | ||
Note: where item 8.7 is less than 2 quarters, all of questions 8.8.1, 8.8.2 and 8.8.3 above must be answered. |
Compliance statement
1 This statement has been prepared in accordance with accounting standards and policies which comply with Listing Rule 19.11A.
2 This statement gives a true and fair view of the matters disclosed.
Date:
Authorised by: Disclosure Committee
(
Notes
1. This quarterly cash flow report and the accompanying activity report provide a basis for informing the market about the entity’s activities for the past quarter, how they have been financed and the effect this has had on its cash position. An entity that wishes to disclose additional information over and above the minimum required under the Listing Rules is encouraged to do so.
2. If this quarterly cash flow report has been prepared in accordance with Australian Accounting Standards, the definitions in, and provisions of,AASB 6: Exploration for and Evaluation of Mineral ResourcesandAASB 107: Statement of CashFlowsapply to this report. If this quarterly cash flow report has been prepared in accordance with other accounting standards agreed by ASX pursuant to Listing Rule 19.11A, the corresponding equivalent standards apply to this report.
3. Dividends received may be classified either as cash flows from operating activities or cash flows from investing activities, depending on the accounting policy of the entity.
4. If this report has been authorised for release to the market by your board of directors, you can insert here: “By the board”. If it has been authorised for release to the market by a committee of your board of directors, you can insert here: “By the [name of board committee–e.g.,
5. If this report has been authorised for release to the market by your board of directors and you wish to hold yourself out as complying with recommendation 4.2 of the ASX Corporate Governance Council’sCorporate Governance Principles and Recommendations, the board should have received a declaration from its CEO and CFO that, in their opinion, the financial records of the entity have been properly maintained, that this report complies with the appropriate accounting standards and gives a true and fair view of the cash flows of the entity, and that their opinion has been formed on the basis of a sound system of risk management and internal control which is operating effectively.
1 Debt drawn downrepresents the aggregate of amounts drawn under the
2 Information on the basis of preparation for the financial information included in this Quarterly Activities report is set out on page 13 below.
3 See basis of preparation of financial information on p13.
4 The number of options represent the number of Jervois shares that will be issued on exercise. The exercise price represents the price to be paid for the Jervois shares when issued.
Copyright (c) 2022 TheNewswire - All rights reserved.
Copyright (c) 2022 TheNewswire - All rights reserved., source